Free Nov-2023 PRINCE2-Agile-Foundation Certification Sample Questions certification Exam [Q21-Q37]

Share

Free Nov-2023 PRINCE2-Agile-Foundation Certification Sample Questions certification Exam

Certification Topics of PRINCE2-Agile-Foundation Exam PDF Recently Updated Questions

NEW QUESTION # 21
Which statement explains the setting of the cost tolerance for a project in an agile context?

  • A. Cost tolerance can be fixed and flexed
  • B. Cost tolerance is flexed
  • C. Cost tolerance is fixed
  • D. Cost tolerance can be fixed or flexed

Answer: B


NEW QUESTION # 22
Which is an advantage of using the PRINCE2 Agile behavior 'collaboration'?

  • A. It allows people to provide cover for one another
  • B. It ensures that there are no surprises
  • C. It uses learning to help improve products
  • D. It uses experimentation to expand requirements

Answer: C


NEW QUESTION # 23
Which is often used during a retrospective to capture lessons?

  • A. A Kanban board
  • B. A Gantt chart
  • C. A burn chart
  • D. A Glad! Sad! Mad! board

Answer: D


NEW QUESTION # 24
Which statement about the 'be on time and hit deadlines' target is CORRECT?

  • A. It ensures that the level of quality is protected
  • B. It allows change to be handled dynamically
  • C. It is achieved by keeping the delivery teams stable
  • D. It helps with planning dependencies within a project

Answer: D


NEW QUESTION # 25
What is an epic?

  • A. A prioritized list of requirements to be delivered in a sprint
  • B. A detailed user story with high business value
  • C. A high-level user story that is quite broad or vague
  • D. The set of products handed over to the users

Answer: C


NEW QUESTION # 26
Which is a typical characteristic of 'business as usual' work?

  • A. It requires a specific dedicated project manager
  • B. It is delivered by an established team
  • C. It is delivered by a temporary team
  • D. It is executed by program management

Answer: B


NEW QUESTION # 27
Which statement about the 'initiating a project' process is CORRECT?

  • A. The impact of frequent releases on quality management should be assessed
  • B. The project solution should be documented in detail in the project product description
  • C. The process should take more time than usual for disruptive projects
  • D. The initiation stage plan should form part of the project plan

Answer: A


NEW QUESTION # 28
What is typically displayed on a board to show progress to people working on a project?

  • A. User story
  • B. Product backlog
  • C. Information radiator
  • D. Agilometer assessment

Answer: C


NEW QUESTION # 29
Which PRINCE2 principle should be followed in order to engage the business, user and supplier stakeholder interests?

  • A. Continued business justification
  • B. Learn from experience
  • C. Tailor to suit the project
  • D. Defined roles and responsibilities

Answer: D


NEW QUESTION # 30
What should the business case state about the minimum viable product (MVP)?

  • A. That the MVP is the same as project viability
  • B. What the MVP is
  • C. When the MVP will be defined
  • D. That the MVP must go into operational use

Answer: D


NEW QUESTION # 31
What information is NOT typically displayed on a burn chart?

  • A. Actual amount of work done
  • B. Effort remaining
  • C. Amount of time elapsed
  • D. Definition of 'ready'

Answer: D


NEW QUESTION # 32
Which TWO statements about the typical tailoring of a checkpoint report in an agile environment are CORRECT?
1) It should be replaced by the project manager attending a daily stand-up.
2) It should be displayed in the form of an information radiator in a team room.
3) It should be produced when the amount to be delivered will result in tolerance being exceeded.
4) It should be produced in a product backlog in the form of prioritized user stories.

  • A. 3 and 4
  • B. 1 and 4
  • C. 2 and 3
  • D. 1 and 2

Answer: C


NEW QUESTION # 33
What is the definition of a timebox?

  • A. A description of the rate of progress a team is making
  • B. A period where work is carried out to achieve a goal
  • C. A regular event that looks at how processes can be improved
  • D. A tool to write a requirement in the form of who, what and why

Answer: B


NEW QUESTION # 34
Which statement describes how the PRINCE2 'starting up a project' process can be applied in an agile environment?

  • A. PRINCE2 requires a disruptive start to a project
  • B. PRINCE2 is predictive, but not emergent
  • C. PRINCE2 requires a lengthy start to a project
  • D. PRINCE2 is predictive and can be emergent

Answer: D


NEW QUESTION # 35
Which statement about the 'protect the level of quality' target is CORRECT?

  • A. It allows change at the detailed level to be handled dynamically
  • B. It is achieved by ensuring that all features are delivered
  • C. It avoids the use of extra people to improve progress during a timebox
  • D. It is unlikely to be achieved if incomplete user documentation is provided

Answer: B


NEW QUESTION # 36
Which statement about the 'accept that the customer doesn't need everything' target is CORRECT?

  • A. It is based on the concept that people generally use a limited number of product features
  • B. It is achieved by ensuring that the operational product has complete documentation
  • C. It is achieved by testing only a few features to deliver on time
  • D. It enables a more accurate final product to be produced

Answer: A


NEW QUESTION # 37
......


Do You Know How To Prepare For the PRINCE2 Agile Foundation Exam?

Is PRINCE2 Agile Foundation Exam Necessary? Here is What You Need To Know

Taking the PRINCE2 Agile Foundation Exam? Here is Your Study Plan: a guide to help people prepare for their PRINCE2 Agile Foundation Exam

The PRINCE2 Agile Foundation Exam is an exam that is attached to the PRINCE2 Agile Practitioner qualification. It allows an individual to display knowledge in the foundations of agile and supports the candidate in studying for the PRINCE2 Agile Practitioner certification exam. Some of the core areas which will be covered within this exam include; Scrum, Kanban, Lean, product backlogs and release planning. Do you want to choose a certification exam for PRINCE2 Agile Foundation? As a professional, you not only need to acquire theoretical knowledge but also practical skills. To pass PRINCE2 Agile Foundation exam, you must be well prepared. The only way to get success in the PRINCE2 Agile Foundation exam dumps is that you should obtain reliable preparatory materials.


PRINCE2 Agile Foundation Certification Exam is designed to test the knowledge and skills of professionals in project management, including project managers, team leaders, and business analysts. PRINCE2-Agile-Foundation exam covers a wide range of topics, including the principles of PRINCE2 Agile, the benefits of using the methodology, the roles and responsibilities of project managers, and the use of different tools and techniques in project management.

 