NEW QUESTION # 18
Below are four of the seven principles on which ISO 9000 series are based. Match a potential benefit to each of the quality management principles (QMP).

Answer:

Explanation:

Explanation:
A screenshot of a chat Description automatically generated

According to the ISO 9000:2015 document, the seven quality management principles are:
Customer focus
Leadership
Engagement of people
Process approach
Improvement
Evidence-based decision making
Relationship management
For each principle, the document provides a statement, a rationale, key benefits, and actions you can take to apply the principle in your organization.
Based on the document, here is a possible way to match a potential benefit to each of the four quality management principles you mentioned:
Table
Quality management principle
Potential benefit
Customer focus
Increased revenue and market share
Engagement of people
Enhanced trust and collaboration throughout the organization
Improvement
Enhanced drive for innovation
Evidence-based decision making
Increased ability to demonstrate effectiveness of past actions


NEW QUESTION # 19
In the context of a third-party certification audit, match the roles with the following responsibilities:

Answer:

Explanation:

Explanation:
In the context of a third-party certification audit, match the roles with the following responsibilities:
Responsibilities:
Conduct the audit to the assigned area.= Auditors
Assist the auditors in identifying personnel to participate in the audit.= Guide Assign each team member's responsibility for the audit.= Audit team leader Respond to questions and provide evidence to the auditor.= Auditee According to ISO 19011:2018, clause 3, the definitions of the roles are as follows1:
Auditors: persons with the competence to conduct an audit
Guide: person appointed by the auditee to assist the audit team
Auditee: organization being audited
Audit team leader: member of an audit team appointed to manage the audit or an audit team Therefore, the roles can be matched to the responsibilities based on these definitions and the description of the audit process in clause 6 of the standard1.
References: ISO 19011:2018(en), Guidelines for auditing management systems


NEW QUESTION # 20
Which of the following two documents does an auditor need to prepare and complete prior to the on-site audit?

  • A. Risk Matrices
  • B. Audit Report
  • C. Checklist / Prompts
  • D. Audit Plan
  • E. Findings
  • F. Procedures

Answer: C,D

Explanation:
According to ISO 19011:2018, clause 6.3, the audit plan is a document that provides the basis for agreement regarding the conduct of the audit. The audit plan should include the information listed in my previous response, such as the audit objectives, scope, criteria, schedule, team, methods, report, etc. The audit plan should be prepared and completed prior to the on-site audit, and should be communicated to the audit team and the auditee1.
According to ISO 19011:2018, clause 6.4.3, the checklist / prompts are documents that list the questions or topics that need to be covered during an audit. The checklist / prompts can help the auditor to collect and verify information relevant to the audit criteria, and to ensure the consistency and completeness of the audit.
The checklist / prompts should be prepared and completed prior to the on-site audit, and should be based on the audit plan and the audit scope and objectives1.
Therefore, the two documents that an auditor needs to prepare and complete prior to the on-site audit are B and D, as they are essential for planning and conducting the audit. The other options are not correct, as they are either prepared or completed after the on-site audit, or not required by the standard:
*A. Audit Report: The audit report is a document that provides a complete, accurate, concise, and clear record of the audit. The audit report should include the information listed in my previous response, such as the audit objectives, scope, criteria, findings, conclusions, etc. The audit report should be prepared and completed after the on-site audit, and should be distributed to the audit client and the auditee1.
*C. Procedures: Procedures are documents that specify the way activities are to be performed. Procedures may be part of the audit criteria, if they are part of the organization's management system, or part of the audit programme, if they are part of the certification body's or registrar's requirements. Procedures are not prepared or completed by the auditor prior to the on-site audit, but rather reviewed or followed by the auditor during the audit1.
*E. Risk Matrices: Risk matrices are tools that help to assess and prioritize the risks and opportunities associated with the audit programme or the audit. Risk matrices may be part of the audit programme management, if they are used to determine and evaluate the audit programme risks and opportunities, or part of the audit preparation, if they are used to determine and evaluate the audit risks and opportunities. Risk matrices are not prepared or completed by the auditor prior to the on-site audit, but rather used or updated by the auditor during the audit programme management or the audit preparation1.
*F. Findings: Findings are the results of the evaluation of the collected audit evidence against the audit criteria.
Findings can indicate either conformity or nonconformity, as well as positive aspects or opportunities for improvement. Findings are not prepared or completed by the auditor prior to the on-site audit, but rather generated and recorded by the auditor during the audit activities1.
References: ISO 19011:2018(en), Guidelines for auditing management systems


NEW QUESTION # 21
Who would be defined as a witness during a witness audit?
Choose two of the following options:

  • A. An existing member of the audit team
  • B. Someone with a qualification from the certification body
  • C. An assessor for the accreditation body
  • D. An auditor

Answer: C,D

Explanation:
Comprehensive and Detailed Explanation: = According to the web search results from my internal tool, a witness audit is a technique used during an accreditation audit, where the accreditation body observes the performance and competence of the certification body auditors in conducting an audit12. A witness audit can also be used by a certification body to monitor and evaluate its own auditors3. During a witness audit, the following roles can be defined:
*An auditor: This is the person who is being witnessed by the accreditation body or the certification body. The auditor is responsible for conducting the audit according to the audit plan, criteria, and standards, and for providing audit evidence and findings123.
*An assessor for the accreditation body: This is the person who witnesses the auditor on behalf of the accreditation body. The assessor is responsible for evaluating the auditor's performance and competence, and for providing feedback and recommendations to the accreditation body123.
The other options are not defined as witnesses during a witness audit, according to the web search results from my internal tool. They are:
*Someone with a qualification from the certification body: This is not a specific role in a witness audit, as anyone who is involved in the audit process should have a qualification from the certification body. Moreover, having a qualification does not necessarily mean that the person is a witness or an auditor4.
*An existing member of the audit team: This is not a specific role in a witness audit, as the audit team consists of the auditors who are conducting the audit, not the ones who are witnessing it. The witness audit is a separate activity from the audit itself, and the witness should not interfere with the audit process or influence the audit outcome123.
Therefore, the correct answer is B and D.
References: 1: DQS Inc. | Witness Audits | Auditor Training 2: Have you ever been involved with a witness audit? - IFSQN 3: Certac - Witness Audit of Certification Bodies 4: ISO 19011:2018 - Guidelines for auditing management systems


NEW QUESTION # 22
Which two of the following are included in the objectives of the 'Stage 1 initial certification audit'?

  • A. To evaluate the operational processes of the organisation.
  • B. To evaluate the performance of monitoring and reviewing activities.
  • C. To review the quality manual.
  • D. To evaluate the internal audit and management review processes.
  • E. To evaluate the preparedness of the organisation for a Stage 2 audit.
  • F. To make a decision on certification to ISO 9001:2015.

Answer: C,E

Explanation:
*To evaluate the preparedness of the organisation for a Stage 2 audit: This objective involves assessing the readiness of the organisation to undergo the Stage 2 audit, where the conformity and effectiveness of the quality management system will be verified123. The audit team will check the level of implementation and understanding of the quality management system, identify any major gaps or nonconformities, and confirm the audit scope, criteria, and plan123.
*To review the quality manual: This objective involves reviewing the documented information of the quality management system, such as the quality policy, the quality objectives, the scope, the processes, and the procedures, to ensure that they meet the requirements of ISO 9001:2015123. The audit team will also evaluate the organisation's understanding and application of the standard, and identify any areas of improvement or concern123.
The other options are not included in the objectives of the Stage 1 initial certification audit, according to the web search results from my internal tool. They may be related to other stages or types of audits, but they are not the focus of the Stage 1 audit.
Therefore, the correct answer is B and D.
References: 1: ISO 9001 Certification Audits | Stage 1 and Stage 2 - 9001. Simplified 2: Stage 1 of your Audit
| NQA Blog 3: Getting Certified to ISO 9001 - the Stage 1 Audit


NEW QUESTION # 23
You have been nominated audit team leader of a third-party audit. Which of the following could be the two most relevant objectives of this audit?

  • A. Evaluate the capability of the management system to establish and achieve objectives
  • B. Identify opportunities for improvement
  • C. Evaluate the effectiveness of the management system
  • D. Evaluate the benefits obtained since the implementation of the management system
  • E. Evaluate the satisfaction interested parties
  • F. Identify the need of resources

Answer: A,C

Explanation:
Evaluate the effectiveness of the management system: This objective involves verifying that the quality management system meets the requirements of a specific standard, such as ISO 9001:2015, and that it achieves the intended results and outcomes. The audit team will collect and analyse audit evidence to determine the degree of conformity and performance of the quality management system23.
*Evaluate the capability of the management system to establish and achieve objectives: This objective involves verifying that the quality management system supports the strategic direction and policies of the organization, and that it addresses the needs and expectations of the interested parties. The audit team will assess the suitability, adequacy, and alignment of the quality management system objectives, and the effectiveness of the planning and implementation processes to achieve them23.
The other options are not the most relevant objectives of a third-party audit, according to the web search results from my internal tool. They may be related to other aspects or types of audits, but they are not the focus of a third-party audit.
Therefore, the correct answer is B and D.
References: 1: Safeguarding Your Business: The Power of Third-Party Security Audits 2: ISO 19011:2018 - Guidelines for auditing management systems 3: Third Party Audit - QMSGurus.com


NEW QUESTION # 24
You work for an organisation, 'A', which provides packaged food to the public. You are asked to lead a team (you as the leader and two other auditors) to audit a supplier, 'B', which provides packaging materials to your organisation. It is 4 p.m. and the audit is close to an end; you are having an internal meeting with the team to decide what will be presented to the auditee during the Closing meeting.
The Closing meeting was scheduled
for 5 p.m.
You, as audit team leader, audited top management, the laboratory, and the storage of raw materials.
Auditor 1 audited the two manufacturing lines and dispatch areas.
You to Auditor 1: "What findings would you report?"
Auditor 1: "When reviewing the Dispatch records, I noticed that during the morning two different trucks (Number 011 and 025) delivered the same batch number of the product (Batch 33555). Truck 011 left the plant at 9.15 am and Truck 025 left the plant at
11.30 am. Procedure P-02 Rev.3 says
that trucks should carry a complete batch. The batch number, once on the truck, is captured using a QR device." You: "OK, what do you think?" Auditor 2: "I think that this is a nonconformity." You: "OK. How would you describe the evidence on which the nonconformity will be based"?
Identify which one of the following statements best describes the identified nonconformity.

  • A. A product delivered to the client was not identified as required in P-02 Rev 3.
  • B. Dispatch personnel do not always carry out its activities in conformance with Procedure P-02 rev 3.
  • C. Dispatch personnel are not fully aware of the need to conform to written procedures.
  • D. The batch 33555 was delivered split in two different trucks (011 and 025).

Answer: D

Explanation:
According to the definition in ISO 9000, a nonconformity is "non-fulfillment of a requirement". There are three parts to a well-documented nonconformity: the audit evidence to support auditor findings; a record of the requirement against which the nonconformity is detected; and the statement of nonconformity1. In this case, the audit evidence is the dispatch records that show the same batch number of the product being delivered by two different trucks at different times. The requirement is the procedure P-02 Rev.3 that says that trucks should carry a complete batch. The statement of nonconformity is that the batch 33555 was delivered split in two different trucks (011 and 025), which does not conform to the procedure. Therefore, option C best describes the identified nonconformity, as it includes all three parts of a well-documented nonconformity.
Option A is not correct, as it does not state the audit evidence or the requirement. Option B is not correct, as it does not specify the audit evidence or the statement of nonconformity. Option D is not correct, as it does not match the audit evidence or the requirement. References: 1: ISO 9001 Auditing Practices Group Guidance on Nonconformity - Documenting.


NEW QUESTION # 25
During a second-party audit of a dairy farm (by a potential customer) complying with ISO 9001:2015, the auditor verifies that there is large variability in the daily production of the milking yard. The current agreement with their only customer is to provide 2,000 litres per day. However, in the last two years, they have noticed an increasing variability in daily production.
If they produce less than 2,000 litres, they are penalised with a fine of 1.5 pesos for every litre that they do not provide. If they produce more than 2,000 litres, they use the extra milk to feed the pigs.
This process has been in operation for decades. The dairy farm was founded by the grandfather of the current owners, who did not want to alter the established practices.
The auditor raises a nonconformity on the basis that the process is not under control (Clause 8.1).
If you had been the auditor, which one of the following actions would you have accepted?

  • A. Retain the current contract and try to sell the occasional surplus milk to a second customer.
  • B. Apply the existing process of addressing the risks and opportunities of milk production.
  • C. Modify the contract with the current customer to provide them with only 1,500 litres of milk per day and make an agreement with a second customer.
  • D. Analyse the daily dispatch of milk for 7 days to determine its variability.

Answer: B

Explanation:
The action that the auditor would have accepted is:
*Option B: Apply the existing process of addressing the risks and opportunities of milk production. This option is correct because ISO 9001:2015 clause 8.1 requires the organization to plan, implement and control the processes needed to meet the requirements for the provision of products and services, and to implement actions determined in clause 6.1, which refers to the actions to address risks and opportunities. The organization should apply the existing process of addressing the risks and opportunities of milk production, which may include identifying the sources of variability, assessing the potential impacts and consequences, determining and implementing appropriate actions to reduce or eliminate the variability, monitoring and measuring the effectiveness of the actions, and reviewing and updating the actions as necessary.
The following options are not correct:
*Option A: Modify the contract with the current customer to provide them with only 1,500 litres of milk per day and make an agreement with a second customer. This option is not correct because it does not address the root cause of the variability in the daily production of the milking yard, which may affect the quality and consistency of the products and services provided by the organization. It also does not demonstrate the organization's commitment to meet the customer and applicable statutory and regulatory requirements, as required by ISO 9001:2015 clause 8.2.2.
*Option C: Retain the current contract and try to sell the occasional surplus milk to a second customer. This option is not correct because it does not address the root cause of the variability in the daily production of the milking yard, which may affect the quality and consistency of the products and services provided by the organization. It also does not demonstrate the organization's commitment to meet the customer and applicable statutory and regulatory requirements, as required by ISO 9001:2015 clause 8.2.2.
*Option D: Analyse the daily dispatch of milk for 7 days to determine its variability. This option is not correct because it does not address the root cause of the variability in the daily production of the milking yard, which may affect the quality and consistency of the products and services provided by the organization. It also does not demonstrate the organization's commitment to implement actions to address risks and opportunities, as required by ISO 9001:2015 clause 8.1.
References:
*ISO 9001:2015 Quality management systems - Requirements, Clause 8: Operation, Subclause 8.1:
Operational planning and control, Subclause 8.2: Requirements for products and services
*ISO 9001 Lead Auditor Course Material, Module 4: ISO 9001:2015 Requirements, Slide 23: Clause 8 - Operation
*ISO 9001 Lead Auditor Training Course - IRCA Certified, Section 4.2: ISO 9001:2015 Requirements, Subsection 4.2.8: Clause 8 - Operation
*Lead Auditor Exam Preparation Guide (EPG) Template - PECB, Section 3.2: Exam Content Outline, Subsection 3.2.1: Section 1 - Audit Fundamentals, Subsection 3.2.2: Section 2 - Audit Principles, Subsection
3.2.3: Section 3 - Audit Process, Subsection 3.2.4: Section 4 - Audit Competencies


NEW QUESTION # 26
You are carrying out an annual audit at an organisation that offers home security services. You are interviewing the Quality Manager (QM) You: "Would you tell me about your management review process?" QM: "The senior management team plans to review the management system every six months. The review follows a set agenda and records are maintained." You: "May I see the records from the last two management reviews?" Narrative: The Quality Manager gives you the latest record, which shows the last management review took place nine months ago.
The Quality Manager then gives you the previous management review record, which took place one year before the latest review.
You: "Are there any other review reports in the last two years?
QM: "No, these are the only ones."

Answer:

Explanation:

Explanation:

Nonconformity report
ISO 9001 Clause Number: 9.3.1 Nature of problem: Management review has not been conducted at the defined frequency. ISO 9001 requirement that has not been fulfilled: ISO 9001 - "Top management shall review the organization's quality management system at planned intervals." Evidence: The last management review took place nine months ago, and the previous one took place one year before the latest review. The planned interval is six months.


NEW QUESTION # 27
Select six of the activities that are specifically required by ISO 17021-1 as part third-party (Certification Body) surveillance audit processes.

  • A. Failing to meet financial responsibilities.
  • B. Review the calibration status of the instrumentation.
  • C. Review the status of previously raised findings and audit effectiveness of any outstanding findings.
  • D. Confirm effectiveness of internal audit and management review.
  • E. Verify legal compliance.
  • F. Complete a full document review of the quality management system.
  • G. Handling of customer complaints since last visit.
  • H. Review changes to the QMS since last visit.
  • I. Conduct a minimum number of annual surveillance audits during the certification period.
  • J. Audit use of certification marks on marketing materials.

Answer: C,D,E,G,H,J

Explanation:
The activities that are specifically required by ISO 17021-1 as part of third-party (Certification Body) surveillance audit processes are:
*Option A: Audit use of certification marks on marketing materials. This option is correct because ISO
17021-1:2015 clause 9.6.2.2 requires the certification body to audit the client's use of marks and/or any other reference to certification, as applicable, to ensure conformity with the certification requirements.
*Option B: Review changes to the QMS since last visit. This option is correct because ISO 17021-1:2015 clause 9.6.2.2 requires the certification body to review any changes affecting the client's quality management system and its ability to continue to fulfil the requirements of the standard used for certification.
*Option C: Confirm effectiveness of internal audit and management review. This option is correct because ISO
17021-1:2015 clause 9.6.2.2 requires the certification body to confirm the continuing effectiveness of the client's quality management system, including the effectiveness of the internal audit and management review processes.
*Option F: Review the status of previously raised findings and audit effectiveness of any outstanding findings.
This option is correct because ISO 17021-1:2015 clause 9.6.2.2 requires the certification body to review the status of findings and any corrective actions taken by the client in response to previous audits, and to verify the effectiveness of the implemented corrective actions.
*Option H: Verify legal compliance. This option is correct because ISO 17021-1:2015 clause 9.6.2.2 requires the certification body to verify the client's compliance with applicable statutory and regulatory requirements related to the scope of certification.
*Option I: Handling of customer complaints since last visit. This option is correct because ISO 17021-1:2015 clause 9.6.2.2 requires the certification body to review the client's handling of customer complaints related to the certified activities since the last audit.
The following options are not correct:
*Option D: Complete a full document review of the quality management system. This option is not correct because ISO 17021-1:2015 clause 9.6.2.2 does not require the certification body to complete a full document review of the quality management system during surveillance audits. A full document review is only required during the initial certification audit or when there are significant changes to the quality management system or the certification requirements.
*Option E: Failing to meet financial responsibilities. This option is not correct because ISO 17021-1:2015 clause 9.6.2.2 does not require the certification body to audit the client's financial responsibilities during surveillance audits. The certification body may have contractual arrangements with the client regarding the payment of fees, but this is not part of the surveillance audit process.
*Option G: Review the calibration status of the instrumentation. This option is not correct because ISO
17021-1:2015 clause 9.6.2.2 does not require the certification body to review the calibration status of the instrumentation during surveillance audits. The certification body may audit the client's monitoring and measuring resources as part of the quality management system requirements, but this is not a specific activity required by ISO 17021-1.
*Option J: Conduct a minimum number of annual surveillance audits during the certification period. This option is not correct because ISO 17021-1:2015 clause 9.6.2.2 does not require the certification body to conduct a minimum number of annual surveillance audits during the certification period. The certification body may determine the frequency and duration of surveillance audits based on the risk and performance of the client, but this is not a specific activity required by ISO 17021-1.
References:
*ISO 17021-1:2015 Conformity assessment - Requirements for bodies providing audit and certification of management systems - Part 1: Requirements
*ISO 9001 Lead Auditor Course Material, Module 7: Audit Follow-up and Surveillance, Slide 8: Surveillance Audit
*ISO 9001 Lead Auditor Training Course - IRCA Certified, Section 7.2: Audit Follow-up and Surveillance
*Lead Auditor Exam Preparation Guide (EPG) Template - PECB, Section 3.2: Exam Content Outline, Subsection 3.2.1: Section 1 - Audit Fundamentals, Subsection 3.2.2: Section 2 - Audit Principles, Subsection
3.2.3: Section 3 - Audit Process, Subsection 3.2.4: Section 4 - Audit Competencies


NEW QUESTION # 28
XYZ Corporation is an organisation that employs 100 people. As the audit team leader, you conduct a certification audit at Stage 1. When reviewing the quality management system (QMS), you find that the objectives have been defined by an external consultant using those of a competitor, but nothing is documented.
The Quality Manager complains that this has created a lot of resistance to the QMS, and the Chief Executive is asking questions about how much it will cost.
Which two options describe the circumstances in which you could raise a nonconformity against clause 6.2 of ISO 9001?

  • A. Quality objectives are not maintained as documented information.
  • B. The organisation cannot afford to undertake quality objectives all at once.
  • C. Quality objectives were not established in alignment with the organisation's quality policy.
  • D. Quality objectives are not being implemented by the organisations' personnel.
  • E. The consultant has not interpreted ISO 9001 correctly.
  • F. Establishing quality objectives did not include top management.

Answer: A,C

Explanation:
According to ISO 9001:2015, clause 6.2.1, the organization is required to establish quality objectives at relevant functions, levels, and processes for the quality management system (QMS). The quality objectives must be consistent with the quality policy, measurable, monitored, communicated, and updated as appropriate.
The organization is also required to maintain documented information on the quality objectives, as per clause
7.5.1.
Therefore, in the scenario given, the quality objectives defined by the external consultant are not in alignment with the organization's quality policy, as they are based on those of a competitor, rather than the organization's own purpose, strategic direction, and customer requirements. This creates a mismatch between the organization's vision and goals, and the quality objectives that are supposed to guide and measure the QMS performance. Moreover, the quality objectives are not maintained as documented information, which makes it difficult to communicate, monitor, and update them, as well as to demonstrate evidence of their implementation and achievement.
Hence, the circumstances in which a nonconformity against clause 6.2 of ISO 9001 could be raised are B and C, as they indicate a failure to comply with the requirements of clause 6.2.1. The other options are either irrelevant or not directly related to clause 6.2, as they do not pertain to the establishment and documentation of quality objectives.
References:
ISO 9001:2015(en), Quality management systems - Requirements, clause 6.2.1 and 7.5.1 ISO 19011:2018(en), Guidelines for auditing management systems, clause 6.4.4 and 6.7.2 ISO 9001 Lead Auditor Training Course | IRCA Certified | BSI, section "Learning objectives" ISO 9001 Lead Auditor Course Material | 3FOLD Education Centre, module 5 and 6


NEW QUESTION # 29
Below are four of the seven principles on which ISO 9000 series are based. Match a potential benefit to each of the quality management principles (QMP).

Answer:

Explanation:

Explanation:
Quality management principles:
Customer focus = Increased revenue and market share
Engagement of people = Enhanced trust and collaboration throughout the organisation Improvement = Enhanced drive for innovation Evidence-based decision-making = Increased ability to demonstrate effectiveness of past actions According to the Quality management principles document published by ISO, each quality management principle has a statement, a rationale, key benefits, and actions you can take to apply it. Based on these descriptions, the potential benefits can be matched to the corresponding principles as follows:
Customer focus: The primary focus of quality management is to meet customer requirements and to strive to exceed customer expectations. The key benefits of this principle include increased customer value, customer satisfaction, customer loyalty, repeat business, reputation, customer base, revenue and market share.
Engagement of people: Competent, empowered and engaged people at all levels throughout the organization are essential to enhance its capability to create and deliver value. The key benefits of this principle include improved understanding of the organization's objectives and values, increased involvement in improvement activities, enhanced personal development, increased motivation and empowerment, enhanced trust and collaboration, and increased recognition and rewards.
Improvement: Successful organizations have an ongoing focus on improvement. The key benefits of this principle include improved organizational capabilities, alignment of improvement activities at all levels, increased ability to anticipate and react to opportunities and threats, enhanced drive for innovation, and increased levels of satisfaction.
Evidence-based decision-making: Decisions based on the analysis and evaluation of data and information are more likely to produce desired results. The key benefits of this principle include improved decision-making processes, increased ability to demonstrate the effectiveness of past decisions, increased ability to review, challenge and change opinions and decisions, and increased ability to improve performance.


NEW QUESTION # 30
Select which one of the following statements is true.

  • A. A technical expert can replace a qualified auditor on an audit team.
  • B. Audits leading to auditor qualification are undertaken annually.
  • C. An audit team can include non-qualified auditors.
  • D. The team leader shall be an auditor that is qualified in the scheme.

Answer: D

Explanation:
According to the ISO 19011:2018 standard, which provides guidelines for auditing management systems, the team leader of an audit team should be an auditor who has demonstrated the competence to manage an audit of the relevant management system scheme. This means that the team leader should have the appropriate knowledge, skills, and experience to plan, conduct, report, and follow-up an audit of the specific management system, such as ISO 9001 for quality management systems. The other options are false because: B. An audit team can include non-qualified auditors, but only as observers or trainees who do not contribute to the audit findings or conclusions. C. A technical expert can assist a qualified auditor on an audit team, but cannot replace them, as a technical expert does not have the competence to perform audits. D. Audits leading to auditor qualification are not undertaken annually, but rather as part of a certification process that involves meeting certain criteria, such as education, work experience, audit experience, and examination. References:
ISO 19011:2018, PECB Certified ISO 9001 Lead Auditor Exam Preparation Guide, ISO 9001:2015 Quality Management Systems Lead Auditor Training Course


NEW QUESTION # 31
Select the term that best describes the purpose of retaining documented information in a quality management system to ISO 9001.

  • A. To safeguard the integrity of the quality management system.
  • B. To provide confidence in the effectiveness of the quality management system.
  • C. To facilitate auditing for proof of conformity to the standard.
  • D. To support the operation of the processes of the quality management system.

Answer: D

Explanation:
Documented information is a means by which an organization demonstrates compliance. It communicates what we do and how we do things, it communicates what happened and what results were achieved. It is, essentially, a tool for communication. ISO 9001:2015 allows an organization flexibility in the way it chooses to document its quality management system (QMS). This enables each individual organization to determine the correct amount of documented information needed in order to demonstrate the effective planning, operation and control of its processes and the implementation and continual improvement of the effectiveness of its QMS. The standard states that the organization shall maintain documented information to the extent necessary to support the operation of processes and retain documented information to the extent necessary to have confidence that the processes are being carried out as planned. Therefore, the purpose of retaining documented information is to support the operation of the processes of the QMS, not to facilitate auditing, provide confidence or safeguard integrity, which are secondary benefits of documented information.
References: Guidance on the requirements for Documented Information of ISO 9001:2015, ISO 9001:2015 documented information | CQI | IRCA, Documented Information Required by ISO 9001:2015 - 9000 Store


NEW QUESTION # 32
You are carrying out an audit at a single-site organisation seeking certification to ISO 9001 for the first time.
The organisation manufactures
cosmetics for major retailers.
You are interviewing the Manufacturing Manager (MM).
You: "I would like to begin by looking at the cleaning controls."
MM: "We record the cleaning of the equipment at the end of every batch. This document details the minimum cleaning frequency and the procedures to follow for all areas and each item of equipment. The person who carries out the cleaning puts their initial on the document and records the time and date alongside." Narrative: You sample production records over 3-days and note down evidence of nonconformity as per the table below.

Answer:

Explanation:


NEW QUESTION # 33
......