Latest Success Metrics For Actual C_TS412_2021 Exam 2024 Realistic Dumps [Q26-Q46]

Share

Latest Success Metrics For Actual C_TS412_2021 Exam 2024 Realistic Dumps

Updated C_TS412_2021 Dumps Questions For SAP Exam


SAP Certified Application Associate - SAP S/4HANA Project Systems (C_TS412_2021) certification exam is designed to validate the skills and knowledge of individuals who work with SAP S/4HANA Project Systems. C_TS412_2021 exam tests the candidate's ability to configure and implement SAP S/4HANA Project Systems, including project structures, procurement, and cost management. SAP Certified Application Associate - SAP S/4HANA Project Systems certification is a globally recognized standard for professionals working in project management and SAP S/4HANA Project Systems.


To take the SAP C_TS412_2021 exam, candidates must have a solid understanding of SAP S/4HANA Project Systems and relevant project management concepts. They should also have experience in configuring and implementing SAP S/4HANA Project Systems solutions. C_TS412_2021 exam consists of 80 multiple-choice questions and has a time limit of 180 minutes. Upon successful completion of the exam, candidates will receive the SAP Certified Application Associate - SAP S/4HANA Project Systems certification, which is recognized worldwide and can help to advance their careers in project management and implementation.

 

NEW QUESTION # 26
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component ?

  • A. Set up the requirement date aligned with the activity start date and a negative offset of 5 days
  • B. Set up the requirement date aligned with the activity start date and an offset of 5 days
  • C. Set up the requirement date manually as February 5.
  • D. Set up the requirement date aligned with the activity finish date and an offset of 15 days.

Answer: A

Explanation:
To set up the requirement date for the component so that it will be in stock 5 days in advance of the assembly activity, you should set up the requirement date aligned with the activity start date and a negative offset of 5 days. The requirement date is the date on which a material component is required for an activity. The offset is a value that shifts the requirement date forward or backward from the activity start or finish date. A negative offset means that the requirement date is earlier than the activity date. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 27
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct answers to this question

  • A. The procurement type of the material must be internal
  • B. The exact lot size procedure must be used
  • C. The materials must allow sales order or project stock
  • D. An MRP group must be assigned

Answer: A,B


NEW QUESTION # 28
Which objects can be used to specify settlement rules? Note: There are 2 correct answers to this question?

  • A. Network header for activity-account-assigned networks
  • B. Standard WBS elements
  • C. Network activity for activity-account-assigned networks
  • D. WBS elements

Answer: A,D

Explanation:
The objects that can be used to specify settlement rules are network header for activity-account-assigned networks and WBS elements. A settlement rule is a parameter that defines how the actual costs incurred for a project object are allocated, in whole or in part, to one or more receivers. A settlement rule contains various attributes, such as the receiver type, the receiver number, the settlement percentage, and so on. The objects that can be used to specify settlement rules are:
Network header for activity-account-assigned networks: A network header is a structural element of a network that contains general data and settings for a network, such as its order type, number range, scheduling parameters, and so on. A network header for activity-account-assigned networks means that the network has its activities assigned to different account assignments, such as cost centers, orders, or sales orders. A network header for activity-account-assigned networks can be used to specify a settlement rule for settling the costs of the network to one or more receivers.
WBS elements: A WBS element is a structural element of a project that represents a deliverable or a work package within a project. A WBS element can have various attributes, such as dates, costs, revenues, budgets, and so on. A WBS element can be used to specify a settlement rule for settling the costs of the WBS element to one or more receivers.


NEW QUESTION # 29
You are using budgeting and active availability control. How can availability control be activated? Note: There are 2 correct answers to this question

  • A. Background activation (CJBV - Activate Availability Control) l
  • B. Automatic activation with assignment to an investment program
  • C. Automatic activation with budget assignment
  • D. Automatic activation with the first actual posting

Answer: A,C


NEW QUESTION # 30
Float time is calculated during scheduling. Which of the following statements about float time are correct? Note: There are 3 correct Answers to this question.

  • A. By default, critical activities have a float time, which is less than or equal to zero.
  • B. Float time can be negative.
  • C. Activities with the time constraint "Must start on" always have a negative float time.
  • D. The maximum size of a free float is as large as the total float of an activity.
  • E. The float time of WBS elements is calculated by extrapolation.

Answer: A,B,C


NEW QUESTION # 31
What could be a reason to use expert mode in the valuation method for results analysis?

  • A. Valuation in different currencies
  • B. Assignments of different accounts for postings to financial accounting
  • C. Billing WBS elements belonging to different company codes
  • D. Usage of different line ID

Answer: D

Explanation:
One reason to use expert mode in the valuation method for results analysis is usage of different line ID. Results analysis is a function that allows you to calculate and post values for work in process (WIP), reserves for unrealized costs (RUC), profit from sales order stock (PSOS), and so on. Results analysis uses valuation methods to determine how these values are calculated based on various criteria, such as cost of sales method, percentage of completion method, revenue-based method, and so on. Expert mode is a type of valuation method that allows you to define your own logic and rules for results analysis by using formulas and conditions. One reason to use expert mode in the valuation method for results analysis is usage of different line ID. A line ID is a parameter that identifies a line item in results analysis data. A line ID can have various attributes, such as cost element group, value category, posting indicator, and so on. By using expert mode in the valuation method for results analysis, you can use different line ID for different scenarios or requirements that are not covered by the standard valuation methods. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 32
You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget?

  • A. Results analysis
  • B. Easy Cost Planning
  • C. Availability control
  • D. Cost forecast

Answer: C


NEW QUESTION # 33
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct answers to this question

  • A. Saving a purchase order
  • B. Saving a service entry shee
  • C. Saving a goods receipt
  • D. Saving a supplier invoice

Answer: B,C


NEW QUESTION # 34
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?

  • A. Activate commitment management in the project definition Enter the budget in the master data of the top WBS element
  • B. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing
  • C. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element
  • D. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element

Answer: B

Explanation:
To solve the problem of the system not preventing their project managers from exceeding their budgets, you have to activate availability control in the assigned budget profile and define the tolerance limits in customizing. The budget profile is a parameter that defines the basic settings for budgeting in your project, such as whether availability control is active or not. The tolerance limits are values that specify how much deviation from the budget is allowed before the system issues warnings or error messages. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


NEW QUESTION # 35
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct answers to this question

  • A. The procurement type of the material must be internal
  • B. The exact lot size procedure must be used
  • C. An MRP group must be assigned
  • D. The materials must allow sales order or project stock

Answer: C,D

Explanation:
Requirements grouping of materials is a process that allows you to plan and procure materials jointly for several WBS elements within a project or across projects. To use requirements grouping of materials, the materials must allow sales order or project stock, which means they must have a special procurement type of E or Q in the material master. An MRP group must also be assigned to the materials, which defines the parameters for material requirements planning, such as lot size and planning strategy. Reference: https://help.sap.com/doc/78f5c353b677b44ce10000000a174cb4/700_SFIN20%20006/en-US/0814c353b677b44ce10000000a174cb4.html


NEW QUESTION # 36
Which sets of dates can be used to schedule networks? Note: There are 2 correct Answers to this question.

  • A. Basic dates
  • B. Baseline dates
  • C. Planned dates
  • D. Forecast dates

Answer: A,D


NEW QUESTION # 37
How can you search in the structure overview based on the user status? Note: There are 2 correct answers to this question

  • A. By searching for the individual status
  • B. By searching for the status profile
  • C. By searching via status combination code
  • D. By searching via status selection profile

Answer: A,D

Explanation:
To search in the structure overview based on the user status, you can use either the status selection profile or the individual status as search criteria. The structure overview is a function that allows you to display and analyze various structural elements of a project, such as WBS elements, networks, activities, milestones, and so on. The structure overview also provides various search functions that allow you to find specific project objects based on different criteria, such as number, description, system status, user status, and so on. To search in the structure overview based on the user status, you can use either:
The status selection profile: This is a parameter that allows you to define a set of user statuses that can be used as a filter for searching project objects. You can create and maintain status selection profiles in Customizing for Project System under Structures Status Management Define Status Selection Profiles . You can also assign a default status selection profile to a project profile or a network profile.
The individual status: This is a parameter that allows you to enter a single user status as a search criterion for finding project objects. You can enter an individual status directly in the search dialog box of the structure overview.


NEW QUESTION # 38
Cost & Budget
You are using network and internal activities in your project . You have already create a purchase requisition and the bid invitation., and have entered the quotation ...
What is the typical sequence for the following business transactions and document.

  • A. Vendor selection - purchase order handing- purchase order monitoring- Benefic Check- Acceptance of performed services.
  • B. Benefic check - Acceptance of performed service- vendor selection - purchase order handing- purchase order monitoring-Good receipt - invoce ..
  • C. Vendor selection- Purchase order handing-purchase order monitoring-Good receipt- Invoice receipt.
  • D. Vendor selection - purchase order handing - invoice receipt - purchase order monitoring -Good receipt.

Answer: C


NEW QUESTION # 39
What are the prerequisites for delivering materials from the project? Note: There are 2 correct Answers to this question.

  • A. A delivery document type must be configured.
  • B. A sales order must be created in advance.
  • C. A sold to party is necessary.
  • D. A shipping point is necessary.

Answer: C,D


NEW QUESTION # 40
To which object can you assign a factory calendar?

  • A. Milestone
  • B. Material component
  • C. Relationship
  • D. Network header

Answer: D


NEW QUESTION # 41
You want to use subnetworks during the project. Which of the following statements describes subnetworks?

  • A. A subnetwork cannot be defined for a superior subnetwork.
  • B. The scheduling type of a subnetwork is always copied from the superior network
  • C. Maintenance orders can be defined as sub-network
  • D. Subnetworks must be scheduled separately from the superior network

Answer: B

Explanation:
One statement that describes subnetworks is that the scheduling type of a subnetwork is always copied from the superior network. A subnetwork is a network that covers only part of a project and is linked in relationships with other subnetworks in the same project. A subnetwork can be used to refine and detail your networks as planning progresses. The scheduling type is a parameter that determines how the dates of activities and networks are calculated based on their dependencies and constraints. The scheduling type of a subnetwork is always copied from the superior network when creating or changing a subnetwork. The scheduling type of a subnetwork cannot be changed independently from the superior network. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/f373bb53707db44ce10000000a174cb4.html


NEW QUESTION # 42
Which of the following statements are true? Choose the correct answers. There are 2 correct answers to this question.

  • A. You can also represent a project using a WBS and one or more networks.
  • B. You cannot use the characteristics of both the structures (WBS and Networks) together to represent a project.
  • C. You can create a project based on a Activity.
  • D. You can map a project using only one WBS or one network.

Answer: A,C

Explanation:
You can use both WBS and networks to represent a project in SAP S/4HANA Project System. A WBS shows the hierarchical structure of the project, while a network shows the flow and dependencies of the project activities." According to SAP Blogs3, "You can create a project based on an activity by using the app 'Create Project from Activity'." Reference: 13


NEW QUESTION # 43
Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to this question

  • A. In the project profile
  • B. In the operative WBS element
  • C. In the project version
  • D. In the project definition of a standard WBS
  • E. In the project type

Answer: A,B,D


NEW QUESTION # 44
When you create a service activity in your network, what data can be entered? Note: There are 3 correct Answers to this question.

  • A. Service purchase order number
  • B. Service specification
  • C. Vendor
  • D. Overall limit (maximum value of all unplanned services)
  • E. Material master within service specification

Answer: B,C,D


NEW QUESTION # 45
What PP/DS master data is necessary for using PP/DS? Note: There are 2 correct Answers to this question.

  • A. Resource
  • B. Production version
  • C. Location
  • D. Material

Answer: A,C


NEW QUESTION # 46
......