NEW QUESTION 42
The correct sequence of events in using Scrum framework is as follows:
- A. Sprint Planning, Sprint, Sprint Retrospective, Daily Scrum, and Sprint Review
- B. Sprint Planning, Daily Scrum, Sprint, Sprint Review, and Sprint Retrospective
- C. Sprint Planning, Sprint, Daily Scrum, Sprint Review, and Sprint Retrospective
- D. Sprint Planning, Sprint, Sprint Retrospective, Daily Scrum, and Sprint Review
Answer: C
NEW QUESTION 43
The Sprint Goal is selected before the Sprint Backlog is created.
- A. True
- B. False
Answer: A
NEW QUESTION 44
A _____________________ is created during the first half of the Sprint planning meeting and a
_________________ is created during the second half of the Sprint planning meeting?
- A. Sprint Backlog, collection of tasks
- B. Product Backlog, Sprint Backlog
- C. Sprint Goal, Sprint Backlog
- D. Product Backlog, collection of tasks
Answer: C
NEW QUESTION 45
What is the primary way a Scrum Master keeps a Development Team working at its highest level of productivity?
- A. By preventing changes to the Backlog once the Sprint begins
- B. By ensuring the meetings start and end at the proper time
- C. By keeping high value features high in the Product Backlog
- D. By facilitating Development Team decisions and removing impediments
Answer: D
NEW QUESTION 46
Why does Scrum prevent Product Owners from changing Product Backlog items that are being worked on during the Sprint?
- A. A Sprint cycle is not enough time for senior management review and approve changes
- B. This forces Product Owners to focus on what is really important for the team to develop.
- C. The development team cannot meet their Sprint commitment to complete work if requirements are changing
- D. The development team must be able to limit the Product Owner authority
Answer: B
NEW QUESTION 47
Agile software development also promotes industry best practices that ____________ and
- A. Emphasize team members; partner involvement
- B. Emphasize managers; stakeholder involvement
- C. Emphasize teamwork; customer involvement
- D. Emphasize software developers; manager involvement
Answer: C
NEW QUESTION 48
The individual, detailed pieces of work that are needed to convert a product backlog item into a working software component or solution are called:
- A. Line items
- B. Tasks
- C. Use cases
- D. User Stories
Answer: B
NEW QUESTION 49
How should items in the Product Backlog be ordered?
- A. Alphabetically first and then by list order in the Product Backlog
- B. Prioritized by business importance first. The items that result in biggest ROI, must be priorized first;
- C. Chronologically by date of original business request first and then by list order in the Product Backlog
- D. Grouped by business features first and then chronologically by date of original business request
Answer: B
NEW QUESTION 50
In an Agile environment, planning happens at which two levels? (Choose two.)
- A. release planning
- B. sprint planning
- C. product planning
- D. backlog planning
Answer: A,B
NEW QUESTION 51
What is the maximum time that Scrum recommends the team spend in the daily scrum (daily standup)?
- A. As long as it takes
- B. Four hours
- C. Thirty minutes
- D. One hour
- E. Fifteen minutes
Answer: E
NEW QUESTION 52
When many Scrum Teams are working on the same product, should all of their increments be integrated every Sprint?
- A. No, that is far too hard
- B. No, each Scrum Team stands alone
- C. Yes, otherwise Product Owners may not be able to inspect what is done accurately
- D. Yes, but only the Scrum's Teams whose work has dependencies
Answer: C
NEW QUESTION 53
Which three activities will a Product Owner likely engage in during a Sprint?
- A. Prioritize the Development Team's activities.
- B. Run the daily Scrum
- C. Answer questions from the Development Team about items in the current Sprint
- D. Provide feedback
- E. Work with the stakeholders
- F. Update the Sprint burndown chart
Answer: C,D,E
NEW QUESTION 54
_____________ constitute the Sprint Backlog and are often estimated in hours.
- A. Features
- B. Tasks
- C. Use Cases
- D. Stories
Answer: B
NEW QUESTION 55
Which statement best describes what it means for an activity to be time-boxed?
- A. There is a recommended amount of time for the activity
- B. There is a maximum time limit for the activity
- C. The activity must take place on a particular date
- D. The activity must start at a particular time
Answer: B
NEW QUESTION 56
Which of the following are artifacts associated with Scrum?
- A. Effort chart
- B. Product specification
- C. Sprint backlog
- D. Product owner list
Answer: C
NEW QUESTION 57
________________ constitute the Sprint Backlog and are often estimated in hours?
- A. Features
- B. Tasks
- C. Use Cases
- D. User Stories
Answer: B
NEW QUESTION 58
A _____________________ is created during the first half of the Sprint planning meeting and a
_________________ is created during the second half of the Sprint planning meeting?
- A. Product Backlog, Sprint Backlog
- B. Sprint Goal, Sprint Backlog
- C. Sprint Backlog, collection of tasks
- D. Product Backlog, collection of tasks
Answer: C
NEW QUESTION 59
Who should know the most about the progress toward a business objective or a release, and be able to explain the alternatives most clearly?
- A. The Development Team
- B. The Project Manager
- C. The Scrum Master
- D. The Product Owner
Answer: D
Explanation:
Explanation/Reference:
NEW QUESTION 60
How many hours per day should a person on a Scrum team work?
- A. However many hours are needed to get the work done.
- B. A sustainable pace, usually from 7-8 hours per day.
- C. An "ideal day" measuring only when he or she is productive.
- D. 14 hours.
Answer: B
NEW QUESTION 61
From the activities given, which is the latest step in sequence of the Scrum framework?
- A. Sprint retrospective
- B. Sprint review
- C. Sprint planning
- D. Daily scrum
Answer: A
NEW QUESTION 62
True or False: Story Points are for sizing, not for time estimation?
- A. True
- B. False
Answer: A
NEW QUESTION 63
A line in the Agile Manifesto reads, "____________ and _____________ over processes and tools". Please select which option best completes the statement.
- A. Individuals; Interactions
- B. Customer; Individuals
- C. People; Relationships
- D. Customers; Employees
Answer: A
NEW QUESTION 64
What is the primary responsibility of the Scrum Master?
- A. To Prioritize the Product Backlog
- B. To manage the Development Team
- C. To remove any impediments the Development Team encounters during their work
- D. To work with the Product Owner to develop the Product Backlog
Answer: C
NEW QUESTION 65
What is the maximum amount of time that the team should spend in the daily scrum?
- A. 45 minutes
- B. As long as it takes
- C. 1 hour
- D. 15 minutes
- E. 15 minutes, proportionally less for shorter Sprints
Answer: D
NEW QUESTION 66
What is the primary objective of the daily scrum?
- A. To give a status report to the Scrum Master on what each member has completed in the Sprint, what each member will work on next, and to report progress roadblocks.
- B. To share with the team what each member has completed in the Sprint, what each member will work on next, and to report progress roadblocks
- C. To give a status report to the Product Owner on what each member has completed in the Sprint, what each member will work on next, and to report progress roadblocks.
- D. To discuss work details with the team since every team member must attend the meeting
Answer: B
NEW QUESTION 67
......
Ultimate Guide to Prepare CSM-001 Certification Exam for GAQM certification: https://www.testkingit.com/GAQM/latest-CSM-001-exam-dumps.html